ENERGY TRANSITION · INDIAProject IntelligenceSOURCE-LINKED · INDIA
TRANSMISSION • CAPITAL ALLOCATION INTELLIGENCE

Read the grid milestones.
Understand the evidence.

Applicant-level renewable generation capacity, substations and expected connectivity dates from an official CTUIL listing. Each record separates source facts from unanswered investment questions.

CTUIL primary sourceSnapshot, not live statusExpected ≠ actual connectivity
▤
Connectivity applications—Unique CTUIL application IDs
ϟ
Generation capacity represented—Reported solar + wind MW
◈
Deemed GNA represented—Reported MW; separate from generation MW
⌕
Historical dates needing review—Expected dates already passed; no delay inferred
EVIDENCE NAVIGATOR

Connectivity milestone register

Filter by applicant, substation or region. Select a record to inspect the exact source description, dated milestone and open questions.

Primary source · CTUIL
Critical distinction: A CTUIL expected connectivity / GNA effective date is not a commissioned-project date. A past expected date only indicates that a fresh source check is needed; it is not proof of a delay. Storage in MWh is not added to generation MW.
SOURCE RECHECKSecond register observation

The same ten public CTUIL rows were reviewed again. Identical displayed fields do not verify operational status or absence of changes outside this subset.

Recheck date loading…
Applicant / ApplicationStateSubstationGenerationDeemed GNAExpected date
CROSS-DOCUMENT INTELLIGENCE

Evidence that changes the question

Exact application-ID matches across official historical CTUIL documents. Investigate field definitions, shared transmission dependencies and missing completion proof before forming an investment view.

Official documents · historical, not live
Applications with additional official documents—Matched by exact CTUIL application ID
Documented source observations—Schedules and technical facts as stated
Source-reconciliation questions—Not a verified delay, error or financial risk score
Shared grid-system relationships—Design/scope relationships; operation unverified
Source interpretation: the register, JCC meeting minutes and historical GNA grant records may describe different measurements or scheduling concepts. Differences are shown as review questions, never automatic investment alerts. Actual connectivity, financial closure and commissioning still require newer primary evidence.
HISTORICAL GRANT EVIDENCE

From grant dates to evidence of actual connection

Application-specific status as stated in a separately labelled CTUIL grant file. A historical “Not effective” entry and a scheduled firm date do not establish today's connected/commissioned status.

Period labelled Jan 2026 · not current
Grant-list applications matched—Exact applicant, ID, capacity and substation
Historic “Not effective” statements—Status in an older document only
Current effectiveness orders proven0No upgrade from this source
The CTUIL file is labelled January 2026 in its filename, but an exact issue/as-of day has not been independently established. A firm GNA start date is a distinct documented field from the expected date on the contemporary register. This historical document is not a new November 2026 status check or a commissioning certificate.
PRIMARY ENGINEERING EVIDENCE

Project coordinates & transmission-bay amendments

Original CTUIL in-principle intimations identify generating-station locations and allocated transmission bays. These are source-declared coordinates and historical approval changes, not verified parcel boundaries, constructed bays or live power connections.

Application-matched intimation letters
Officially declared generating locations—As printed in dated CTUIL documents
Documented bay revisions—Changed approval record, not energization
New shared pooling relationships—Grid design, actual completion unknown

Formal connectivity-intimation amendments

Interpretation: a CTUIL "Location of the Generating Station" coordinate identifies the declared project location, not a surveyed boundary or actual individual turbine/solar equipment location. A letter reallocating bay 206 to 217 or 214 to 215 documents an approval change, not a completed or energized bay. Current connectivity and commissioning checks are unaffected.
INVESTOR RESEARCH · DOCUMENTARY DEPENDENCIES

Asset-to-grid dependency explorer

Select an application to review documented grid allocation, engineering relationships and the primary evidence still needed before investment conclusions.

Historical evidence · Current status unresolved
DOCUMENTARY EVIDENCE · HISTORICAL

Asset and transmission evidence timeline

Trace exact CTUIL application documents separately from broader Kurnool-III infrastructure leads. Compare dates without treating planned milestones or procurement awards as proof of commissioning.

No current operation inferred

Evidence qualification: Timeline dates are the issue/meeting/contract dates of historical records. A site-level electrical-layout award cannot be tied to Hero Solar's bays without independent scope evidence. The 2025 JCC's developer-reported statements require verification against original minutes. No dated final effective order, charging certificate or COD is established by this timeline.

INVESTMENT DUE DILIGENCE

Official-source verification workbench

Six independent evidence gates per application: effective connectivity, physical grid readiness, land/financial closure, commissioning, offtake and equipment specifications. No green verified status is shown without an application-specific official document.

Unknown ≠ negative finding
Applications reviewed—Original CTUIL application IDs
Evidence checks tracked—Six separate gates per ID
Application-specific statuses evidenced—Verified only with dated primary decisions
Unresolved verification gates—Not equivalent to failure or non-compliance

Priority source questions

    The source-category links go to official registers and document collections. They are not proof that the selected project appears there. A specific dated application-matched effective order, commissioning certificate, compliance decision or approved amendment must be inspected before a status can be upgraded. No automated scraping or third-party paid feed is used.

    MATERIAL CHANGE INTELLIGENCE

    Verified change events

    Future snapshots are compared using exact application IDs and dated official evidence. Proposed changes require review before publication.

    ↻
    No reviewed change events yet

    This is the initial source baseline, not a claim that no real-world changes have occurred. The repository includes a comparator for future dated snapshots; unverified differences are not published as investment signals.

    DATA COVERAGE

    What we do not yet know

    The initial ten dossiers identify relevant records, but do not establish project commissioning, final grid access, PPA, land compliance or capex. Those are the next sources to connect.

    Review official CTUIL register ↗