Read the grid milestones.
Understand the evidence.
Applicant-level renewable generation capacity, substations and expected connectivity dates from an official CTUIL listing. Each record separates source facts from unanswered investment questions.
Connectivity milestone register
Filter by applicant, substation or region. Select a record to inspect the exact source description, dated milestone and open questions.
The same ten public CTUIL rows were reviewed again. Identical displayed fields do not verify operational status or absence of changes outside this subset.
| Applicant / Application | State | Substation | Generation | Deemed GNA | Expected date |
|---|
Evidence that changes the question
Exact application-ID matches across official historical CTUIL documents. Investigate field definitions, shared transmission dependencies and missing completion proof before forming an investment view.
From grant dates to evidence of actual connection
Application-specific status as stated in a separately labelled CTUIL grant file. A historical “Not effective” entry and a scheduled firm date do not establish today's connected/commissioned status.
Project coordinates & transmission-bay amendments
Original CTUIL in-principle intimations identify generating-station locations and allocated transmission bays. These are source-declared coordinates and historical approval changes, not verified parcel boundaries, constructed bays or live power connections.
Formal connectivity-intimation amendments
Asset-to-grid dependency explorer
Select an application to review documented grid allocation, engineering relationships and the primary evidence still needed before investment conclusions.
Asset and transmission evidence timeline
Trace exact CTUIL application documents separately from broader Kurnool-III infrastructure leads. Compare dates without treating planned milestones or procurement awards as proof of commissioning.
Evidence qualification: Timeline dates are the issue/meeting/contract dates of historical records. A site-level electrical-layout award cannot be tied to Hero Solar's bays without independent scope evidence. The 2025 JCC's developer-reported statements require verification against original minutes. No dated final effective order, charging certificate or COD is established by this timeline.
Official-source verification workbench
Six independent evidence gates per application: effective connectivity, physical grid readiness, land/financial closure, commissioning, offtake and equipment specifications. No green verified status is shown without an application-specific official document.
Priority source questions
The source-category links go to official registers and document collections. They are not proof that the selected project appears there. A specific dated application-matched effective order, commissioning certificate, compliance decision or approved amendment must be inspected before a status can be upgraded. No automated scraping or third-party paid feed is used.
Verified change events
Future snapshots are compared using exact application IDs and dated official evidence. Proposed changes require review before publication.
This is the initial source baseline, not a claim that no real-world changes have occurred. The repository includes a comparator for future dated snapshots; unverified differences are not published as investment signals.
What we do not yet know
The initial ten dossiers identify relevant records, but do not establish project commissioning, final grid access, PPA, land compliance or capex. Those are the next sources to connect.